Ïã¸ÛÁùºÏ²Ê¹ÙÍø

Coronavirus Resources District information pertaining to Coronavirus (COVID-19)

Student Services Remodel

Project Status

FCC Student Services Modernization
Measure E Budget:
$300,000
Total Expenses to Date:
$75,792
Balance:
$224,208

Construction is in complete and the project was accepted at the June 2007 Board meeting. Final invoices are being received and processed, with the expectation that the final balance of the project will be reduced to zero.

Construction is in progress.

Construction is in progress.

Project Title: FCC Student Services Modernization
Funding Source: State (Eligible for Measure E)

Project Description: The project will modernize the existing 29,646 sq. ft. Student Services Building. The building contains offices, admissions and records processing area, the campus health clinic, men’s and women’s restrooms, 1 st and 2 nd floor entry lobby expansion, HVAC, data and electrical upgrades. Measure E General Obligation Bond Funds will be used to fund $ 234,436 for the temporary portable buildings.

Anticipated Completion Date: 2007

Status: Project was awarded at the May 2, 2006 Board Meeting and construction began June 2006.

Estimated Project Budget: Prepared by Teter Architects and Engineers

Funding Source: State
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 298,400 81,145 210,855 184,057 30,000 265,202
Fees & Other Charges 43,663 1,448 29,800 29,800 0 31,248
Construction & Equipment 2,984,000 0 200,000 23,415 200,000 23,415
Inspection & Testing 123,840 0 14,000 7,000 0 7,000
Contingency 208,880 0 0 0 0 0
Total 3,748,303 86,240 468,961 256,578 232,000 342,818

Project Title: FCC Student Services Modernization
Funding Source: State (Eligible for Measure E)

Project Description: The project will modernize the existing 29,646 sq. ft. Student Services Building. The building contains offices, admissions and records processing area, the campus health clinic, men’s and women’s restrooms, 1 st and 2 nd floor entry lobby expansion, HVAC, data and electrical upgrades. Measure E General Obligation Bond Funds will be used to fund $ 234,436 for the temporary portable buildings.

Anticipated Completion Date: 2007

Status: Project bids April 2006 and will be taken to the Board for award May 2006.

Estimated Project Budget: Prepared by Teter Architects and Engineers

Funding Source: State
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 292,000 81,145 210,855 153,783 40,968 234,928
Consultant Services 84,090 3,647 42,000 8,675 2,000 12,322
Fees & Other Charges 52,942 1,448 51,494 19,090 0 20,538
Construction & Equipment 2,893,000 0 200,000 0 0 0
Inspection & Testing 133,000 0 20,000 0 0 0
Contingency 202,510 0 0 0 0 0
Total 3,657,542 86,240 524,349 181,548 42,968 267,788

Funding Source: State (Eligible for Measure E)

Project Description: The project will modernize the existing 29,646 sq. ft. Student Services Building. The building contains offices, admissions and records processing area, the campus health clinic, men’s and women’s restrooms, 1 st and 2 nd floor entry lobby expansion, HVAC, data and electrical upgrades. Measure E General Obligation Bond Funds will be used to fund $ 234,436 for the temporary portable buildings.

Anticipated Completion Date: 2007

Status: Working Drawings were submitted to DSA for approval in August 2005.

Estimated Project Budget: Prepared by Teter Architects and Engineers

Funding Source: State
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 292,000 50,500 230,000 45,500 165,700 96,000
Consultant Services 84,090 2,544 42,000 1,962 28,816 4,506
Fees & Other Charges 52,942 1,448 51,494 0 0 1,448
Construction & Equipment 2,893,000 0 200,000 0 0 0
Inspection & Testing 133,000 0 20,000 0 0 0
Contingency 202,510 0 0 0 0 0
Total 3,657,542 54,492 543,494 47,462 194,516 101,954

Funding Source: State (Eligible for Measure E)

Project Description: The project will modernize the existing 29,646 sq. ft.Student Services Building.The building contains offices, admissions and records processing area, the campus health clinic, men’s and women’s restrooms, 1st and 2nd floor entry lobby expansion, HVAC, data and electrical upgrades. Measure E General Obligation Bond Funds will be used to fund $ 234,436 for the temporary portable buildings.

Anticipated Completion Date: 2007

Status: Teter Architects is proceeding with Working Drawings and will submit to the DSA in August 2005.

Estimated Project Budget: Prepared by Teter Architects and Engineers

Funding Source: State
  Estimated Project Budget 2002-05 Actual Expenditures 2005-06 Budget 2005-06 Expenditures to date 2005-06 Encum-brances Total Expenditures
Design Services 292,000 50,500 230,000 0 0 50,500
Consultant Services 84,090 2,544 42,000 0 0 2,544
Fees & Other Charges 52,942 1,448 51,494 0 0 1,448
Construction & Equipment 2,893,000 0 200,000 0 0 0
Inspection & Testing 133,000 0 20,000 0 0 0
Contingency 202,510 0 0 0 0 0
Total 3,657,542 54,492 543,494 0 0 54,492

State Chancellor’s Office has approved Preliminary Plans and has given approval to proceed to Working Drawings.

Preliminary Plans are complete and have been submitted to the State Chancellor’s Office for review and approval to proceed to Working Drawings.