Ïã¸ÛÁùºÏ²Ê¹ÙÍø

Coronavirus Resources District information pertaining to Coronavirus (COVID-19)

Health/Fitness Center

Project Status

 

FCC Health Fitness Center (Physical Performance Center)
Measure E Budget: $1,699,576
Total Expenses to Date: $1,457,010
Balance: $242,566

Construction is complete and was accepted at the July 2007 Board meeting. Final invoices are being received and processed, with the expectation that the final balance of the project will be reduced to zero.

Construction is in progress.

Construction is in progress.

Project Title: FCC Health / Fitness Center
Funding Source: Measure E

Project Description: The project will construct new facilities on the east side of campus (east side of Blackstone Blvd.). The facility will include classrooms, offices, and labs for the FCC physical education and athletics programs.

Anticipated Completion Date: Fall/Winter 2007

Status: Project was awarded at the May 2, 2006 Board Meeting and construction began June 2006.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

118,699

21,433

47,168

43,168

4,000

64,601

Consultant Services

39,080

1,461

5,000

4,681

319

6,142

Fees & Other Charges

31,297

2,800

12,000

10,255

0

13,055

Construction & Equipment

1,329,000

0

21,000

0

0

0

Inspection & Testing

116,500

3,200

7,500

3,750

0

6,950

Contingency

65,000

0

0

0

0

0

Total

1,699,576

28,894

92,668

61,854

4,319

90,748

Project Title: FCC Health / Fitness Center
Funding Source: Measure E

Project Description: The project will construct new facilities on the east side of campus (east side of Blackstone Blvd.). The facility will include classrooms, offices, and labs for the FCC physical education and athletics programs.

Anticipated Completion Date: Fall/Winter 2007

Status: Project bids April 2006 and will be taken to the Board for award May 2006.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

91,478

21,433

55,107

36,371

4,000

57,804

Consultant Services

26,769

1,461

8,000

1,295

400

2,756

Fees & Other Charges

15,999

2,800

12,000

8,549

0

11,349

Construction & Equipment

1,336,240

0

21,000

0

0

0

Inspection & Testing

92,923

3,200

5,000

0

0

3,200

Contingency

44,615

0

0

0

0

0

Total

1,608,024

28,894

101,107

46,215

4,400

75,109

Funding Source: Measure E

Project Description: The project will construct new facilities on the east side of campus (east side of Blackstone Blvd.). The facility will include classrooms, offices, and labs for the FCC physical education and athletics programs.

Anticipated Completion Date: Fall/Winter 2007

Status: BCA Architects has conducting preliminary meetings with District to develop schematic design. BCA submitted schematic design to Office of State Architect for preliminary review and comments regarding access compliance. BCA currently proceeding with Working Drawings.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

71,385

17,607

 

16,170

38,936

33,777

Consultant Services

26,769

1,461

8,000

367

6,838

1,828

Fees & Other Charges

15,999

2,800

8,000

6,164

0

8,964

Construction & Equipment

1,356,333

0

21,000

0

0

0

Inspection & Testing

92,923

2,059

5,000

0

0

2,059

Contingency

44,615

0

0

0

0

0

Total

1,608,024

23,927

42,000

22,701

45,774

46,628

Funding Source: Measure E

Project Description: The project will construct new facilities on the east side of campus (east side of Blackstone Blvd.).The facility will include classrooms, offices, and labs for the FCC physical education and athletics programs.

Anticipated Completion Date: 2007

Status: BCA Architects has conducting preliminary meetings with District to develop schematic design.BCA submitted schematic design to Office of State Architect for preliminary review and comments regarding access compliance. BCA currently proceeding with Working Drawings.

Estimated Project Budget: Prepared by Kitchell - Program Manager

Funding Source: Measure E

 

Estimated Project Budget

2002-05
Actual Expenditures

2005-06
Budget

2005-06
Expenditures to date

2005-06
Encum-brances

Total Expenditures

Design Services

71,385

17,607

30,000

0

0

17,607

Consultant Services

26,769

1,461

5,000

0

0

1,461

Fees & Other Charges

15,999

2,800

0

0

0

2,800

Construction & Equipment

892,308

0

21,000

0

0

0

Inspection & Testing

92,923

2,059

5,000

0

0

2,059

Contingency

44,615

0

0

0

0

0

Total

1,143,999

23,927

61,000

0

0

23,927

BCA Architects has conducting preliminary meetings with District to develop schematic design. BCA will submit schematic design to Office of State Architect for preliminary review and comments regarding access compliance by May 2005. BCA and the District will then proceed with programming and design development.

Architect approval by Board is scheduled for January 11, 2005. Programming and schematic design will begin Spring semester of 2005.